Thu, 19 Nov 1998: Butinge terminal partially completed …



22 for 8.8 million Dutch guilder ($4.7 million).Ivan Doloshicki, general manager of Butinges Nafta, said the work that Smit has done at Butinge was beyond his expectations."The company has worked with exceptional professionalism and maintained the highest level of safety and environmental standards," spokesman for Williams Lithuania, Darius Silas, quoted Doloshicki as saying.The terminal, currently under construction, will be completed by the end of 1999, though partial exports of crude oil are planned for as early as this winter.In order to start exporting oil, a pipeline must be completed in Mazeikiai. Doloshicki forecasts the construction to be finished sometime around Jan. 18, 1999."The oil export will start in about a week, as soon as ... Read the rest of this entry »